Sentrum Data Centre

Skerritt Electrical Ltd was commissioned to supply and install the new electrical services for a bespoke Tier 3 N+1 10,000sqft Data Centre in Woking Surrey.

  • sentrum-1
  • sentrum-2
  • sentrum-3

Project Details

Location: Woking, Surrey
Size: 10,000sqft
Client: Sentrum

The contract works involved the installation of the following systems including the full design and coordination of containment systems associated with this new facility

  • MV/LV Mains Distribution Cabling
  • Inter-trip Cabling
  • Cabling to MV Generators
  • Data Centre Earth Nests
  • External Earth Nests
  • General and Emergency Lighting
  • Data Centre A+B Busbar Network
  • Small Power
  • Containment for Specialist Trades
  • L1 Fire Alarm System
  • Water Leak Detection
  • Full load bank testing

The contract duration was 20 weeks, with the project completed on time and within budget.

  • We have used Skerritt Electrical for over ten years on several of our industrial and office schemes. They always offer an outstanding service and display excellent workmanship, and the jobs they do are professionally undertaken to the highest standard. Stoford would recommend them without reservation.

    Matt Burgin Stoford
  • We have used Skerritts for the past five years on a variety of schemes including retail, residential, education and commercial. The quality of their service is excellent from tender stage to project sign off. They have been involved on a number of schemes for us where we have a requirement for BREEAM or The Code for Sustainable Homes. Skerritts have always been proactive in working with us and our consultants to help us achieve these requirements.  We would have no hesitation in recommending Skerritts.

    Martin Gallagher Deeley Construction
  • Having worked on a great many projects with Skerritt Electrical, we are pleased to see them selected for new projects. They are communicative and professional through the design stages and their installations are to a very high standard, with the few items of remedial work taken care of quickly and without complaint. We are happy to put them forward for a great variety of projects.

    Chris Batham-Read ESC
lhmSentrum Data Centre